New Children's Hospital

Currently under construction on the QEII Medical site in Nedlands, adjacent to Kings Park, the new $1.2 billion children's hospital will replace Princess Margaret Hospital for Children.

Due for completion in 2015, the 274-bed state-of-the-art hospital will house WA's only paediatric trauma centre, an integrated research and education facility - including the Telethon Institute for Child Health Research. It will also include all other services currently provided by Princess Margaret Hospital including rehabilitation services and specialist burns and oncology units.

As Perth's leading paediatric care and research facility, it will also offer more family facilities, including bedside accommodation and family resource lounges, along with a larger operating theatre capacity and more neonatal intensive care beds.

Hero

Building for our kids' health

New Children's Hospital Hero
Featured image

Latest tweet

For all the latest info about major projects happening in #Perth visit http://www.getthebiggerpicture.com Perth_Traffic

Video

Play video

New Children's Hospital
Project Time Lapse

Info

Fact

SAME LENGTH AS HAY ST MALL

Key Features

  • 274 beds including 75% single rooms; 25% two-bed rooms
  • Increased outpatient, day-stay and operating theatre capacity
  • Integrated research and education facility
  • Increased family facilities including bedside accommodation and family resource lounges
  • A high dependency unit for high risk patients which will be located alongside the intensive care unit
  • Increased beds and secure facilities for patients with mental health disorders
  • 24 hour access to onsite paediatric pathology service
  • Increased neonatal intensive care beds
  • Increased retail space and staff amenities
  • 78,000sqm of floor space - the same length as the Hay St Mall

Delivery Phases

January 2012 Construction commenced

Mid 2012 Foundation works commence

Mid-late 2012 Structural works commence

Early 2013 Fit-out works commence

Mid 2014 Facade works commence

Early 2014 Structure complete

Mid 2014 Facade complete

Late 2014 Commissioning commenced

Mid 2015 Commissioning complete

Late 2015 Construction work finishes